Re: Spawning jobs in a staggered start?
From: |
Ole Tange |
Subject: |
Re: Spawning jobs in a staggered start? |
Date: |
Mon, 26 Nov 2012 22:58:39 +0100 |
On Sun, Nov 25, 2012 at 8:43 PM, John <da_audiophile@yahoo.com> wrote:
> d>> Is there a way to have parallel spawn jobs on a delayed start with 1 sec
>
>> delay between each one?
>>
>> No. Can you elaborate why that would be useful to you?
>
>
> I am using parallel to send jobs to a compiler in an i686 chroot via the
> schroot command. I have found it to be very fragile and breaks when parallel
> hits it with multiple requests at the same time. If I could add a 1 or 2 sec
> delay between starts, it would be fine. Is this something you can add easily?
Try git version:
seq 10 | time parallel --delay 0.2 echo
/Ole